The Far d’Empordà · Alt Empordà

Pedestrian connection to the viewpoint, El Far d’Empordà

SECOMI urbanized the outdoor public spaces of the municipal facilities that house the dispensary and the El Far d’Empordà elderly care center, on a plot of 452.46 m² acquired by the municipality. The task was to open a pedestrian walkway that would connect the upper square —between Processó Street and Tramuntana Street— with the terrace of the elderly care center, located at a much lower elevation and accessible from Cristòfol Colom Street. There is a significant difference in elevation between the two levels, and to overcome it, almost everything had to be built: retaining walls, steps, terraces, and four sections of stairs.

The work was carried out in eight phases, from the demolition of the building and existing walls to the irrigation and lighting installations. The retaining walls are 30 cm reinforced concrete; the slab of the lower plaza staircase is 15 cm, and the expansion of the upper plaza is a massive slab of 20 cm supported on two IPE-330 profiles anchored to the existing pillars. The finish was key to making the intervention not noticeable: the walls were clad with the same stone from the public building and the rest was rolled up and painted in the already present shade, giving continuity to the urban renewal the town had begun in 2013. The native vegetation planted in abundance on all the embankments is what is now dissolving the weight of the concrete.

Main data of the work:

  • Type of performance: urban works of public space and new pedestrian connection between two levels
  • Playing area: 452.46 m²
  • Equipment: Municipal dispensary and nursing home
  • Executed phases: Previous work and demolition · earthworks · foundation and retaining walls · drainage · structure, footings and concrete pavement · masonry and urbanisation · locksmithing · installations
  • Containment walls: 30 cm thick reinforced concrete
  • Losas: 15 cm wide staircase; expansion of the upper square by 20 cm over two IPE-330 profiles
  • Ramps and terraces: 15 cm reinforced concrete soleras with a dry layer of 20 cm river gravel
  • Staircase floor: Prefabricated concrete parts from Breinco — Superstep and Bordillo Jardín TJ7, 50×7×25 cm
  • Locksmith: handrail and balustrade handrails of 60×10 mm, 200×10 mm sheet metal pergola and electro-welded mesh screens, all in painted steel
  • Facilities: drainage with perforated pipe and filter gravel, automated irrigation by drip system and LED lighting type beacon IP66 / IK08
  • Urban furniture: prefabricated concrete banks that also prevent the entry of vehicles
SECOMI services related to this project:

The work,
Step by step

Frequently asked questions about this work

With retaining walls and a series of steps to make the journey comfortable. In El Far d’Empordà, we connect the high square of the village on foot with the terrace of the birdhouse at 452.46 m².

The outdoor areas of the municipal facilities that house the dispensary and the elderly people’s center open up a new pedestrian walkway between the upper square —between Processó Street and Tramuntana Street— and the terrace of the facilities.

Yes: parking spaces, access points, walls and pedestrian connections for the municipalities of Girona and the surrounding areas. We explain this on the «Structures and civil works» page.

Can we help you evaluate your work?

Every project has its starting point, its doubts and important decisions. If you have a project in mind, let’s talk. We’ll understand what you need and help you take the next step with confidence.

Projects
related

Medinyà · Gironès

Redevelopment of Dr. Fleming Street, Medinyà

Replacement of the pavement and lighting on Dr. Fleming Street, with a unified design that maintains the promenade condition and allows for outdoor events to be held.

Banyoles · Pla de l’Estany

Stairs leading to the Joan de Palau Lookout, Banyoles

Renovation of the stairs leading to the viewpoint in Banyoles, with stainless steel handrails and integrated LED lighting.

Caldes de Malavella · Selva

New urban collector in Caldes de Malavella

Excavation, installation of large diameter pipes and complete replacement of the urban pavement.
SECOMI
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.